The parts have arrived. Erect the structure as discussed. After that, prepare for running electrical for pump stand on the the east end of the tank.
The latest from 1140 Etcheverry
The parts have arrived. Erect the structure as discussed. After that, prepare for running electrical for pump stand on the the east end of the tank.
The remainder of the cable trays have been installed on the northern side of the tank. For now this is all we will need to run electrical to both of the pump stands. The electrical to the pump stands will not be run until all of the necessary brackets are built for the west pump stand. Once this is done the flexible metal conduit can be run on the cable trays to both the east and west beam stand.